Took me 14 months to notice my punch list was the problem, not my crew
Honestly, I was running a 22 unit townhome job outside of Raleigh and we were stuck at like 96 percent done for almost two months. I kept blaming the subs, kept pushing them to get back out there, kept hearing "we'll be there Tuesday" five times in a row. Then my PM handed me my own punch lists from the last three buildings and it hit me: I was writing stuff like "fix trim" and "touch up paint" with no room number. My crew was walking into units with a list that could mean anything, so they'd guess, miss it, and we'd do the whole dance again. I spent one Saturday retyping every item with a unit number, a location, and a photo attached, and the backlog cleared out in about 9 days. Felt dumb and relieved at the same time. Now I'm wondering if I should go back and redo the lists on the last two buildings the same way, or just let it ride since those are already closed out.