Finished a 12,000 square foot slab in one day with my crew of four
We poured a massive warehouse floor in Boise and got it all bull floated, edged, and broomed before the sun went down. I was sure we'd need a second day, but everything just clicked. Has anyone else pulled off a pour that big with a small team?
2 comments
Log in to join the discussion
Log In2 Comments
nora_park722d ago
Nice. We did a 10,000 footer for a farm equipment shed last fall with just three of us. Had two guys running screeds and I handled the power trowel. The key was having the mix timed perfectly, no waiting around.
5
jakelee2d ago
Three people for that much concrete sounds like a recipe for disaster.